Masonry Work To Begin Tomorrow At Church
August 29, 2016
Tomorrow work is scheduled to begin on repairing the cracks in the concrete walkways around the church.
The cracks were caused by the need to move heavy equipment after they had been poured, both as a matter of poor staging of the construction job and insufficient protection for the walkways over which the machinery traversed.
The parge coat around the base of the exterior foundation masonry wall will also be completed, including some work to repoint the original brickwork on the Ward Avenue facade.