More progress was made on completing the exterior shingling; workers are reaching the steeple getting to the western facade of the building (which few have been observing).

More ceiling vaults were delivered and arranged for installing today. The pendentives are still being manufactured and are scheduled to be delivered next week. These last few pieces of ceiling are to hang over the sanctuary. 

Electrical work continues throughout the building and the accessory lighting system in the basement has been wired. The elevator is substantially complete.

We're still waiting on the water company to begin excavation and installation of the water mains to the building.