The Crane has left the Building

IronworkersThe crane was dissembled and driven off the site today, having finished its assigned tasks. Iron workers continue to weld connections in the steel building frame.

The carpenter is affixing clips to the beams on which the trusses will be installed. Hopefully, the delivery will be next week.

Electricians have installed temporary lighting to the church basement and plumbers have installed the septic and ejection pumps in the basement level. 

 