Today the remaining footings were poured on the western end of the narthex and the vestibule, including the foundation for the elevator.

When I mentioned the elevator to some of the students, they remarked, "The church is going to have a basement?" As you know, the basement will house a meeting room, bathrooms and storage rooms and be accessible by a simple elevator for those who cannot climb or descend stairs. 

 

DSCN1347
The footings along the westernmost extent of the church can be seen along with the rectangular foundation for the passenger elevator.


 





DSCN1345
Preparation for the Forms of the Basement Walls